PECS Commissioning Dashboard
Snapshot 2026-06-17 · 162 records · 27 PLCs · EMA5 site · Priority legend →
🏭
Plant Handover — TGW → Amazon
07 Aug 2026 · EMA5 site commissioning deadline
50
days to go
🔧
Mechanical Fit
54/162 complete
33.3%
108 to do
🔌
Wired
75/162 complete
46.3%
87 to do
⚡
I/O Checked
0/162 complete
0.0%
162 to do
💡 Priority cheat sheet
P0
IOQ passed but incomplete
P1
Fitted+Wired, I/O missing
P2
IOQ ≤ 7 days
P3
IOQ 8–14 days
P4
IOQ 15+ days
P0
Critical Blocker
2conveyors
IOQ passed but Fitted or Wired not green
P1
Commissioning Recovery
8conveyors
Fitted+Wired green, I/O check still missing
⚠
Process Anomalies
21conveyors
Cables run without mechanical landing
Lower priority (for reference)
P2
P2 Imminent
22 · IOQ ≤ 7 days
P3
P3 Near
66 · IOQ 8–14 days
P4
P4 Far
64 · IOQ 15+ days
🧠 Key Insights
6 automated observations from current data
🔧 Per-PLC Conveyor Status
Each conveyor must be green across all 3 phases (Fit → Wire → I/O Check) for completion
Complete
Pending (orange)
Anomaly (red)
Not started
| PLC ⇅ | Conveyors ⇅ | 🚨 Anomalies ⇅ | ⏰ Days to IOQ ⇅ | 🔧 Fit ⇅ | 🔌 Wire ⇅ | ⚡ I/O ⇅ |
|---|---|---|---|---|---|---|
| F902 |
1107
1134
1147
1187
1214
1227
1254
1267
1294
1307
1334
1347
1374
1374
1387
1414
1427
1454
1467
1494
|
20anomalies | 19days |
0/20
|
20/20
|
0/20
|
| F901 |
1108
1123
1138
1153
1168
1183
1198
1213
1228
1243
1256
1273
|
1anomaly | 9days |
11/12
|
12/12
|
0/12
|
| F222 |
1112
1129
|
· | 0days |
0/2
|
0/2
|
0/2
|
| F221 |
1112
1129
1152
1179
|
· | 52days |
0/4
|
0/4
|
0/4
|
| F201 |
1112
1129
1152
1179
|
· | 51days |
4/4
|
4/4
|
0/4
|
| F102 |
1125
1173
1218
|
· | 36days |
0/3
|
0/3
|
0/3
|
| F122 |
1126
1173
1218
|
· | 36days |
0/3
|
0/3
|
0/3
|
| F922 |
1147
1174
1187
1214
1227
1254
1267
1294
1307
1334
1347
1374
1387
1414
1427
1454
1467
1494
1507
1534
|
· | 29days |
0/20
|
0/20
|
0/20
|
| F921 |
1108
1123
1138
1153
1168
1183
1198
1213
1228
1243
1258
1273
|
· | 15days |
0/12
|
0/12
|
0/12
|
| F923 |
1107
1134
1147
1174
1187
1214
1227
1254
1267
1294
1307
1334
1347
1374
1387
1414
1427
1454
1467
1494
1507
1534
|
· | 14days |
1107
1134
1147
1174
1187
1214
1227
1254
1267
1294
1307
1334
1347
1374
1387
1414
1427
1454
1467
1494
1507
1534
0/22
|
1107
1134
1147
1174
1187
1214
1227
1254
1267
1294
1307
1334
1347
1374
1387
1414
1427
1454
1467
1494
1507
1534
0/22
|
1107
1134
1147
1174
1187
1214
1227
1254
1267
1294
1307
1334
1347
1374
1387
1414
1427
1454
1467
1494
1507
1534
0/22
|
| F502 |
1119
1192
1222
|
· | 12days |
3/3
|
3/3
|
0/3
|
| F522 |
1117
1175
1209
|
· | 12days |
0/3
|
0/3
|
0/3
|
| F903 |
1107
1134
1147
1174
1187
1214
1227
1254
1267
1294
1307
1334
1347
1374
1387
1414
1427
1454
1467
1494
|
· | 12days |
20/20
|
20/20
|
0/20
|
| F405 |
1112
1131
|
· | 8days |
2/2
|
2/2
|
0/2
|
| F421 |
1112
1128
|
· | 8days |
0/2
|
0/2
|
0/2
|
| F423 |
1112
1128
|
· | 7days |
0/2
|
0/2
|
0/2
|
| F321 |
1123
1143
1172
1188
|
· | 6days |
0/4
|
0/4
|
0/4
|
| F322 |
1126
1144
|
· | 6days |
0/2
|
0/2
|
0/2
|
| F721 |
1111
1126
|
· | 6days |
0/2
|
0/2
|
0/2
|
| F802 |
1113
1131
1154
1171
|
· | 6days |
4/4
|
4/4
|
0/4
|
| F701 |
1171
1186
|
· | 2days |
2/2
|
2/2
|
0/2
|
| F822 |
1113
1128
1154
1168
|
· | 1days |
0/4
|
0/4
|
0/4
|
| F106 |
1112
1132
|
· | -6days |
0/2
|
0/2
|
0/2
|
| F401 |
1112
1131
|
· | -9days |
2/2
|
2/2
|
0/2
|
| F302 |
1125
1144
|
· | -13days |
2/2
|
2/2
|
0/2
|
| F202 |
1112
1129
|
· | -14days |
2/2
|
2/2
|
0/2
|
| F403 |
1112
1131
|
· | -22days |
2/2
|
2/2
|
0/2
|
⚠ Process anomalies: 21 items
Conveyors with "wired" (orange/red) but mechanical fit NOT green — cables pulled without landing. This violates the Fit → Wire → I/O sequence and should not happen.
View anomalies →Cell colors (from Excel)
Complete
Pending (orange)
Anomaly (red)
P2 imminent
P4 far