PECS Commissioning Dashboard

Snapshot 2026-06-17 · 162 records · 27 PLCs · EMA5 site · Priority legend →

🏭
Plant Handover — TGW → Amazon
07 Aug 2026 · EMA5 site commissioning deadline
50
days to go
🔧
Mechanical Fit
54/162 complete
33.3% 108 to do
🔌
Wired
75/162 complete
46.3% 87 to do
I/O Checked
0/162 complete
0.0% 162 to do
💡 Priority cheat sheet
P0 IOQ passed but incomplete
P1 Fitted+Wired, I/O missing
P2 IOQ ≤ 7 days
P3 IOQ 8–14 days
P4 IOQ 15+ days
P0
Critical Blocker
2conveyors
IOQ passed but Fitted or Wired not green
P1
Commissioning Recovery
8conveyors
Fitted+Wired green, I/O check still missing
Process Anomalies
21conveyors
Cables run without mechanical landing
Lower priority (for reference)
P2
P2 Imminent
22 · IOQ ≤ 7 days
P3
P3 Near
66 · IOQ 8–14 days
P4
P4 Far
64 · IOQ 15+ days
🧠 Key Insights

6 automated observations from current data

View insights →

🔧 Per-PLC Conveyor Status

Each conveyor must be green across all 3 phases (Fit → Wire → I/O Check) for completion

Complete Pending (orange) Anomaly (red) Not started
PLC Conveyors 🚨 Anomalies ⏰ Days to IOQ 🔧 Fit 🔌 Wire ⚡ I/O
F902
1107 1134 1147 1187 1214 1227 1254 1267 1294 1307 1334 1347 1374 1374 1387 1414 1427 1454 1467 1494
20anomalies 19days
0/20
20/20
0/20
F901
1108 1123 1138 1153 1168 1183 1198 1213 1228 1243 1256 1273
1anomaly 9days
11/12
12/12
0/12
F222
1112 1129
· 0days
0/2
0/2
0/2
F221
1112 1129 1152 1179
· 52days
0/4
0/4
0/4
F201
1112 1129 1152 1179
· 51days
4/4
4/4
0/4
F102
1125 1173 1218
· 36days
0/3
0/3
0/3
F122
1126 1173 1218
· 36days
0/3
0/3
0/3
F922
1147 1174 1187 1214 1227 1254 1267 1294 1307 1334 1347 1374 1387 1414 1427 1454 1467 1494 1507 1534
· 29days
0/20
0/20
0/20
F921
1108 1123 1138 1153 1168 1183 1198 1213 1228 1243 1258 1273
· 15days
0/12
0/12
0/12
F923
1107 1134 1147 1174 1187 1214 1227 1254 1267 1294 1307 1334 1347 1374 1387 1414 1427 1454 1467 1494 1507 1534
· 14days
0/22
0/22
0/22
F502
1119 1192 1222
· 12days
3/3
3/3
0/3
F522
1117 1175 1209
· 12days
0/3
0/3
0/3
F903
1107 1134 1147 1174 1187 1214 1227 1254 1267 1294 1307 1334 1347 1374 1387 1414 1427 1454 1467 1494
· 12days
20/20
20/20
0/20
F405
1112 1131
· 8days
2/2
2/2
0/2
F421
1112 1128
· 8days
0/2
0/2
0/2
F423
1112 1128
· 7days
0/2
0/2
0/2
F321
1123 1143 1172 1188
· 6days
0/4
0/4
0/4
F322
1126 1144
· 6days
0/2
0/2
0/2
F721
1111 1126
· 6days
0/2
0/2
0/2
F802
1113 1131 1154 1171
· 6days
4/4
4/4
0/4
F701
1171 1186
· 2days
2/2
2/2
0/2
F822
1113 1128 1154 1168
· 1days
0/4
0/4
0/4
F106
1112 1132
· -6days
0/2
0/2
0/2
F401
1112 1131
· -9days
2/2
2/2
0/2
F302
1125 1144
· -13days
2/2
2/2
0/2
F202
1112 1129
· -14days
2/2
2/2
0/2
F403
1112 1131
· -22days
2/2
2/2
0/2

⚠ Process anomalies: 21 items

Conveyors with "wired" (orange/red) but mechanical fit NOT green — cables pulled without landing. This violates the Fit → Wire → I/O sequence and should not happen.

View anomalies →

Cell colors (from Excel)

Complete
Pending (orange)
Anomaly (red)
P2 imminent
P4 far