⚠ Process Anomalies
Conveyors with "wired" done but mechanical fit not complete — sequence violation
| PLC ⇅ | Conveyor ⇅ | Priority ⇅ | Days to IOQ ⇅ | Issue |
|---|---|---|---|---|
| F901 | 1213 | P4 | 10days | Wired green but Fitted pending — cables run without mechanical landing |
| F902 | 1107 | P3 | 19days | Wired green but Fitted pending — cables run without mechanical landing |
| F902 | 1134 | P3 | 19days | Wired green but Fitted pending — cables run without mechanical landing |
| F902 | 1147 | P3 | 19days | Wired green but Fitted pending — cables run without mechanical landing |
| F902 | 1187 | P3 | 19days | Wired green but Fitted pending — cables run without mechanical landing |
| F902 | 1214 | P3 | 19days | Wired green but Fitted pending — cables run without mechanical landing |
| F902 | 1227 | P3 | 19days | Wired green but Fitted pending — cables run without mechanical landing |
| F902 | 1254 | P3 | 19days | Wired green but Fitted pending — cables run without mechanical landing |
| F902 | 1267 | P3 | 19days | Wired green but Fitted pending — cables run without mechanical landing |
| F902 | 1294 | P3 | 19days | Wired green but Fitted pending — cables run without mechanical landing |
| F902 | 1307 | P3 | 19days | Wired green but Fitted pending — cables run without mechanical landing |
| F902 | 1334 | P3 | 19days | Wired green but Fitted pending — cables run without mechanical landing |
| F902 | 1347 | P3 | 19days | Wired green but Fitted pending — cables run without mechanical landing |
| F902 | 1374 | P3 | 19days | Wired green but Fitted pending — cables run without mechanical landing |
| F902 | 1374 | P3 | 19days | Wired green but Fitted pending — cables run without mechanical landing |
| F902 | 1387 | P3 | 19days | Wired green but Fitted pending — cables run without mechanical landing |
| F902 | 1414 | P3 | 19days | Wired green but Fitted pending — cables run without mechanical landing |
| F902 | 1427 | P3 | 19days | Wired green but Fitted pending — cables run without mechanical landing |
| F902 | 1454 | P3 | 19days | Wired green but Fitted pending — cables run without mechanical landing |
| F902 | 1467 | P3 | 19days | Wired green but Fitted pending — cables run without mechanical landing |
| F902 | 1494 | P3 | 19days | Wired green but Fitted pending — cables run without mechanical landing |