🧠 Key Insights
Automated observations from PECS snapshot 2026-06-17
Process observations
Generated from current data state
⚠️
2 P0 CRITICAL BLOCKER
IOQ passed but fitted or wired NOT green. Immediate intervention required — these gate the handover.
⚠️
8 P1 COMMISSIONING RECOVERY
Fitted+wired green but I/O check still pending. Close the loop with TGW commissioning team.
⚠️
10 IOQ dates OVERDUE
Items with negative days-to-IOQ. Should have been commissioned already. Coordinate with William Collings.
⚠️
21 ANOMALIES in sequence
Conveyors with "wired" (orange/red) but not "fitted" green — cables pulled without mechanical landing. This is a process violation.
⚠️
I/O checks 0% green
None of 162 items have I/O checked yet. Wire → I/O is the critical path to verification — coordinate with controls team.
💡
108 items still pending mechanical fit
Mechanical fit is the foundation — confirm TGW team availability and material readiness.