PRIORITY LEGEND — EMA5 PECS (snapshot 17/06/2026)

Reference for the P0–P4 priority codes used throughout the dashboard

Priority Meaning Criterion Conveyors
P0 CRITICAL BLOCKER IOQ passed + fitted or wired NOT green 2 conveyor
P1 COMMISSIONING RECOVERY IOQ passed + fitted+wired green, I/O NOT green 8 conveyor
P2 IOQ imminent (≤7 days) IOQ between 0 and 7 days from today 22 conveyor
P3 IOQ near (8-14 days) IOQ between 8 and 14 days from today 64 conveyor
P4 IOQ far (15+ days) IOQ more than 14 days from today 66 conveyor

NOTES

Snapshot

17/06/2026 — File generated from the Excel provided by Calum.

Total conveyors
162 across 27 PLCs
Overdue
10 conveyors with passed IOQ date