PRIORITY LEGEND — EMA5 PECS (snapshot 17/06/2026)
Reference for the P0–P4 priority codes used throughout the dashboard
| Priority | Meaning | Criterion | Conveyors |
|---|---|---|---|
| P0 | CRITICAL BLOCKER | IOQ passed + fitted or wired NOT green | 2 conveyor |
| P1 | COMMISSIONING RECOVERY | IOQ passed + fitted+wired green, I/O NOT green | 8 conveyor |
| P2 | IOQ imminent (≤7 days) | IOQ between 0 and 7 days from today | 22 conveyor |
| P3 | IOQ near (8-14 days) | IOQ between 8 and 14 days from today | 64 conveyor |
| P4 | IOQ far (15+ days) | IOQ more than 14 days from today | 66 conveyor |
NOTES
- Criteria based ONLY on the IOQ scheduler + phase completion status.
- NOT considered: conveyor criticality, downstream impact, TGW team availability, materials, dependencies.
- Final priorities to be agreed by Andrea + William Collings (TGW Limited PM UK).
- Scope: all 3 phases (fitted, wired, I/O checked) are TGW responsibility (confirmed by Andrea 17/06).
- Dematic: design + sensor supply only — no installation work.
Snapshot
17/06/2026 — File generated from the Excel provided by Calum.
Total conveyors
162 across 27 PLCs
Overdue
10 conveyors with passed IOQ date